The Offices of Audit and Evaluation supervise and conduct independent and objective audits, evaluations, and other reviews of U.S. Department of Housing and Urban Development (HUD] programs and activities to ensure they operate economically, efficiently, and effectively. This page contains links to our audit and evaluation reports and memoranda.
Requirements Documentation in the U.S. Department of Housing and Urban Development’s Acquisition Process
The U.S. Department of Housing and Urban Development’s (HUD) development of requirements documents is a collaboration across HUD program offices. The Office of the Chief Procurement Officer (OCPO) is responsible for obtaining all goods and services required by HUD efficiently and in the most cost-effective manner possible, while program offices are responsible for preparing the requirements documents and submitting an actionable...
Febrero 06, 2025
Report
#2023-OE-0006
Requirements Documentation in HUD’s Acquisition Process
The Office of Evaluation is initiating an evaluation of requirements documentation in HUD’s acquisition process. Our objective is to assess HUD’s processes for developing and approving requirements documents in the pre-award phase of the acquisition life cycle.
Diciembre 01, 2023
Work Start Notification
#2023-OE-0006
Improvements Are Needed To Ensure That Public Housing Properties Are Inspected in a Timely Manner
We audited the U.S. Department of Housing and Urban Development’s (HUD) Real Estate Assessment Center’s inspection process. The audit objectives were to determine whether the Center (1) ensured that public housing properties were inspected within required timeframes before the coronavirus disease 2019 (COVID-19) pandemic; (2) could improve its Big Inspection Plan for inspecting high-priority non-National Standards for the...
Mayo 23, 2023
Report
#2023-CH-0003
End of Preliminary Research – Program Management Improvement Accountability Act of 2016
The Office of Evaluation began preliminary research related to the Program Management Improvement Accountability Act (PMIAA) of 2016. The objective was to determine how HUD has implemented and complied with the requirements of PMIAA. After completing informational interviews with HUD officials and reviewing related documentation, we have determined that a full evaluation is premature at this time because HUD is still...
Abril 28, 2023
Memorandum
#2022-OE-0006
HUD Could Improve Its Field Service Management Quality Assurance Surveillance Plans
We audited the U.S. Department of Housing and Urban Development’s (HUD) Office of the Chief Procurement Officer’s use of its quality assurance surveillance plan (QASP) for its Atlanta Homeownership Center field service management (FSM) housing contracts. We initiated the audit to support HUD’s priority on increasing efficiency in procurement. An assessment of HUD’s use of its QASP, as part of its 3.10 FSM 5-year contract...
Marzo 30, 2023
Report
#2023-BO-0002
Corrective Action Verification Government Purchase Card Program and Government Travel Card Program Audit Recommendations
We completed a corrective action verification (CAV) of recommendations from prior Office of Inspector General (OIG) audit reports on the U.S. Department of Housing and Urban Development’s (HUD) government purchase cards and government travel cards, both issued January 31, 2020. During our CAV, we followed up on all 10 recommendations from OIG audit report 2020-KC-0001 and all 13 recommendations from OIG audit report 2020-KC-0002. Our...
Agosto 24, 2022
Report
#2022-FO-0006
HUD’s Processes for Managing IT Acquisitions
We reviewed the U.S. Department of Housing and Urban Development’s (HUD) ability to effectively complete information technology (IT) acquisitions. HUD’s IT systems and its modernization plans depend heavily on contractors, yet HUD has historically faced significant challenges with implementing effective acquisition processes. Therefore, HUD’s acquisition capacity represents a key potential risk within HUD’s IT environment. We...
Noviembre 17, 2021
Report
#2020-OE-0004
Corrective Action Verification on HUD's Purchase Card and Travel Card Programs
HUD OIG is conducting a Corrective Action Verification on two prior HUD OIG audits of HUD's Purchase Card and Travel Card programs. The review will verify if the corrective actions taken by the Department on the recommendations issued under reports, 2020-KC-0001 Purchase Card Audit and 2020-KC-0002 Travel Card Audit, addressed the underlying issues and risks.
Mayo 21, 2021
Work Start Notification
#FO-21-0006
HUD's Office of the Chief Procurement Officer Quality Assurance Process of Management and Marketing Contracts
HUD OIG is auditing HUD’s contract administration quality assurance processes over its management & marketing contracts. HUD awarded seven firm-fixed price contracts totaling $8.98 billion to five different vendors. The audit objective is to determine whether HUD effectively administered quality assurance surveillance plans for management & marketing contracts to assist in meeting HUD’s mission.
Mayo 01, 2021
Work Start Notification
#PH-21-0011
HUD's Oversight of REAC Inspections
HUD OIG is auditing HUD's Real Estate Assessment Center (REAC) inspection process. REAC's inspection process helps to ensure decent, safe and sanitary affordable public housing . The audit objectives are to (1) determine whether HUD's Real Estate Assessment Center ensured that, before it postponed physical inspections due to COVID-19, public housing properties were inspected within required timeframes, (2) evaluate the...
Octubre 01, 2020
Work Start Notification
#CH 21 0007
HUD's Processes for Managing IT Acquisitions
To determine if HUD has processes in place to efficiently and effectively conduct information technology (IT) acquisitions.
Agosto 01, 2020
Work Start Notification
#2020-OE-0004
Administration of Procurement Activities under the CARES Act
HUD OIG is auditing HUD's COVID-19 procurement activities. Due to the pandemic, regular contracting requirements were revised to help meet the needs of contractors who did not have access to the Federal work sites or could not complete contracts in a timely manner due to quarantining, social distancing, or other COVID-19 related interruptions. The audit objective is to determine what HUD has done to accommodate contractors'...
Agosto 01, 2020
Work Start Notification
#FW 20 0013
COVID-19 Risk Awareness and Lessons Learned from Audits and Evaluations of the CDBG-DR Program
HUD OIG is performing research to help HUD's Community Development Block Grant Coronavirus pandemic (CDBG-CV) grantees be aware of known risks and lessons learned from audits and evaluations of the Community Development Block Grant Disaster Recovery Program grants (CDBG-DR). The purpose of our research is to issue a report that is intended to assist HUD’s Office of Community Planning and Development (CPD) by developing lessons...
Junio 01, 2020
Work Start Notification
#FW 20 0011