Request indemnification for the 7 of the 11 loans that had material underwriting deficiencies (appendix D). The unpaid balance for these loans is $1.3 million and the estimated potential loss to HUD is $607,598.
2020-LA-1005 | September 03, 2020
Mid America Mortgage, dba 1st Tribal Lending, Pinole, CA, Did Not Always Follow HUD’s Section 184 Program Requirements
Public and Indian Housing
- Status2020-LA-1005-001-AOpenClosed$607,598Funds Put to Better Use
Recommendations that funds be put to better use estimate funds that could be used more efficiently. For example, recommendations that funds be put to better use could result in reductions in spending, deobligation of funds, or avoidance of unnecessary spending.
Closed on December 01, 2022 - Status2020-LA-1005-001-BOpenClosedClosed on December 05, 2022
Require the lender to develop and implement enhanced policies and procedures to ensure electronic signatures from borrowers are properly supported.
- Status2020-LA-1005-001-COpenClosedClosed on February 02, 2024
Require the lender to fully implement its quality control plan with respect to reverifications and provide HUD with periodic reports for 12 months to ensure that it conducts its quality control reviews in accordance with the requirements.
2020-AT-1003 | August 31, 2020
The Housing Authority of the City of Macon-Bibb County, GA, Improperly Executed the HAP Contract for Vineville Christian Towers’ RAD Conversion
Public and Indian Housing
- Status2020-AT-1003-001-AOpenClosed$256,824Funds Put to Better Use
Recommendations that funds be put to better use estimate funds that could be used more efficiently. For example, recommendations that funds be put to better use could result in reductions in spending, deobligation of funds, or avoidance of unnecessary spending.
Closed on October 15, 2020Put $256,824 to better use by cancelling the project-based voucher housing assistance payments contract resulting from the RAD conversion. The Authority should work with HUD and the owner to protect the tenancy of the affected tenants at the time of contract cancellation.
- Status2020-AT-1003-001-BOpenClosed$138,925Questioned Costs
Recommendations with questioned costs identify costs: (A) resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B) that are not supported by adequate documentation (also known as an unsupported cost); or (C) that appear unnecessary or unreasonable.
Closed on July 26, 2021Reimburse its Section 8 program $138,925 in associated administrative fees from non-Federal funds for the improper issuance of tenant protection assistance and an improper conversion to the project-based voucher program.
- Status2020-AT-1003-001-COpenClosedClosed on November 02, 2020
Develop and implement procedures to ensure that forms HUD-50059 and or tenant profiles is received from HUD before providing tenant protection assistance resulting from a completed housing conversion action.
- Status2020-AT-1003-001-DOpenClosedClosed on November 02, 2020
Provide adequate training to staff associated with administering tenant protection and project-based vouchers to help address its lack of familiarity with requirements and ensure compliance with program requirements.
- Status2020-AT-1003-001-EOpenClosedClosed on November 12, 2020
Develop and implement procedures for executing Section 8 Project-Based Voucher Program housing assistance payments contracts related to RAD conversions.
2020-CH-0005 | August 21, 2020
HUD Needs To Improve Its Oversight of Lead in the Water of Multifamily Housing Units
Housing
- Status2020-CH-0005-001-AOpenClosedPriorityPriority
We believe these open recommendations, if implemented, will have the greatest impact on helping HUD achieve its mission to create strong, sustainable, inclusive communities and quality affordable homes for all.
Require lenders to obtain the borrowers’ consent to verify the existence of delinquent Federal taxes with the IRS during loan origination and deny any applicant with delinquent Federal tax debt and no payment plan or a noncompliant payment plan or an applicant refusing to provide consent from receiving FHA insurance to put at least $6.1 billion to better use by avoiding potential future costs to the FHA insurance fund.
Status
To fully address this recommendation, HUD will need to provide evidence that it established a method of borrower consent to verify the existence of delinquent federal taxes including, but not limited to one of the options OIG provided, which were (1) lenders obtaining the borrowers' consent to obtain their tax records directly from the IRS or (2) borrowers accessing their own tax information and submitting it to the lenders.
Implementation of this rule should result in HUD putting $6.1 billion to better use.
Analysis
To fully address this recommendation, HUD will need to provide evidence that it established a method of borrower consent to verify the existence of delinquent federal taxes including, but not limited to one of the options OIG provided, which were (1) lenders obtaining the borrowers' consent to obtain their tax records directly from the IRS or (2) borrowers accessing their own tax information and submitting it to the lenders.
Implementation of this rule should result in HUD putting $6.1 billion to better use.
2020-CH-0004 | August 21, 2020
HUD Needs To Improve Its Oversight of Lead in the Water of Housing Choice Voucher and Public Housing Program Units
Public and Indian Housing
- Status2020-CH-0004-001-AOpenClosedClosed on July 01, 2022
Develop and implement an action plan that includes sufficient policies, procedures, and controls that address households living in assisted units having a sufficient supply of safe drinking water. Such policies, procedures, and controls should include but not be limited to (1) developing and implementing internal procedures to be notified, and share with public housing agencies, when the public water systems’ water exceeds the Environmental Protection Agency’s lead action level and (2) revising HUD’s applicable regulations, providing guidance to public housing agencies and Housing Choice Voucher Program landlords, and taking appropriate actions so that households living in assisted units have a sufficient supply of safe drinking water.
2020-BO-0001 | August 12, 2020
HUD Could Strengthen Controls Over Employee Benefits Expensed at Public Housing Agencies
Public and Indian Housing
- Status2020-BO-0001-001-AOpenClosedClosed on February 01, 2021
Evaluate the risk that employee benefit contributions expensed at PHAs may be unreasonable and, if determined necessary, establish and implement controls to reduce or eliminate the evaluated risk.
- Status2020-BO-0001-001-BOpenClosedClosed on April 13, 2021
Develop and implement additional guidance to ensure that PHAs enter accurate employee benefit data into FASS-PH.
2019-OE-0002a | June 25, 2020
HUD Personally Identifiable Information (PII) Records Protection and Management
Office of Administration
- Status2019-OE-0002a-01OpenClosedClosed on August 27, 2021
Designate a Senior Agency Official for Records Management at the Assistant Secretary level or its equivalent.
- Status2019-OE-0002a-02OpenClosedClosed on August 27, 2021
Update and issue agency formal records policy, including detailed procedures and requirements for completing and maintaining program office and agencywide inventories of systems, records, and PII.
- Status2019-OE-0002a-03OpenClosedClosed on August 13, 2025
Update and obtain final NARA approval of all HUD records retention schedules, including the Capstone email schedule, to comply with Federal requirements, including OMB M-19-21.
- Status2019-OE-0002a-04OpenClosedClosed on August 13, 2025
Develop and approve an enterprise strategy to meet all M-19-21 electronic transition requirements.
- Status2019-OE-0002a-05OpenClosed
Issue a formal policy and requirements for managing CUI.
- Status2019-OE-0002a-06OpenClosedClosed on August 27, 2021
Establish and disseminate a policy on safeguarding or prohibiting the transportation of PII records out of the office for telework purposes.
- Status2019-OE-0002a-07OpenClosedClosed on July 01, 2025
Complete the development of performance measures and establish a formal records evaluation process to measure the effectiveness and progress of the records management program.
- Status2019-OE-0002a-08OpenClosedClosed on August 27, 2021
Standardize processes and duties for all RMLOs.