U.S. flag

An official website of the United States government Here’s how you know

The .gov means it’s official.

Federal government websites often end in .gov or .mil. Before sharing sensitive information, make sure you're on a federal government site.

The site is secure.

The https:// ensures that you are connecting to the official website and that any information you provide is encrypted and transmitted securely.

Export
Date Issued

Community Planning and Development

  •  
    Status
      Open
      Closed
    2024-FW-1002-002-A

    We recommend that HUD require the City to provide monitoring reports and supporting documentation to show that it conducted periodic monitoring of NORA’ s performance and compliance with program rules and regulations and ensured that NORA promptly remedies any findings or concerns. This includes, but is not limited to, ensuring that NORA (1) provides adequate oversight of the contractors providing service under the program and (2) maintains documentation to support eligibility for program participants.

  •  
    Status
      Open
      Closed
    2024-FW-1002-002-B

    We recommend that HUD require the City to develop and implement a methodology for NORA to conduct periodic evaluations at appropriate points during the construction process to assess the quality of the work on all new properties and correct any issues identified.

  •  
    Status
      Open
      Closed
    2024-FW-1002-002-C

    We recommend that HUD require the City to develop and implement a plan for how to review the condition of the property updates and determine where repairs are needed.

  •  
    Status
      Open
      Closed
    2024-FW-1002-002-D

    We recommend that HUD require the City to analyze the effectiveness of the Retrofit program and identify what improvements are needed to better benefit program participants and lessen their burden, to include obtaining input from program participants, and implement those improvements.

  •  
    Status
      Open
      Closed
    2024-FW-1002-002-E
    $5,078
    Questioned Costs

    Recommendations with questioned costs identify costs: (A) resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B) that are not supported by adequate documentation (also known as an unsupported cost); or (C) that appear unnecessary or unreasonable.

    We recommend that HUD require the City to support or repay, from nonfederal funds, $5,078 in the square footage overcharge for work not completed, according to the project design and invoice documentation.

  •  
    Status
      Open
      Closed
    2024-FW-1002-002-F
    $99,347
    Questioned Costs

    Recommendations with questioned costs identify costs: (A) resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B) that are not supported by adequate documentation (also known as an unsupported cost); or (C) that appear unnecessary or unreasonable.

    We recommend that HUD require the City to provide supporting documentation for the 4 program participants that did not have adequate income documentation. If the supporting documentation cannot be provided, repay, from nonfederal funds, $99,347.

  •  
    Status
      Open
      Closed
    2024-FW-1002-002-G

    We recommend that HUD require the City to since the property updates have been completed for the 24 program participants that did not receive the green infrastructure training, provide documentation that any subsequent program participants completed the green infrastructure training workshop before the grant agreement is signed and construction begins.

Housing

  •  
    Status
      Open
      Closed
    2024-CH-0001-001-A
    Priority
    Priority

    We believe these open recommendations, if implemented, will have the greatest impact on helping HUD achieve its mission to create strong, sustainable, inclusive communities and quality affordable homes for all.

    Closed on August 14, 2025

    Develop and implement adequate procedures and controls to ensure that (1) staff issues notices of violation and default within 15 calendar days of the inspection report release date and (2) the Office of Multifamily Asset Management and Portfolio Oversight is made aware when notices are not issued within 15 calendar days after the inspection report release date and takes action as appropriate to ensure that future notices are issued in a timely manner. 

  •  
    Status
      Open
      Closed
    2024-CH-0001-002-A
    Priority
    Priority

    We believe these open recommendations, if implemented, will have the greatest impact on helping HUD achieve its mission to create strong, sustainable, inclusive communities and quality affordable homes for all.

    Closed on July 16, 2025

    Include language in future notices of violation and default clearly stating that owners are required to inspect all units (including vacant units), common areas, grounds, building systems, and sites as part of the owner survey and require owners to include sufficient detail in the surveys to show (1) when the survey was conducted and (2) that the survey was a complete survey of the project.

  •  
    Status
      Open
      Closed
    2024-CH-0001-002-B
    Closed on August 05, 2025

    Develop and implement adequate policies, procedures, and controls to ensure that owner certifications and surveys and other relevant documents related to properties that fail inspections or are noted as having EHS deficiencies are maintained and retrievable from an easily accessible location.

  •  
    Status
      Open
      Closed
    2024-CH-0001-002-C
    Closed on June 25, 2025

    Develop and implement adequate controls to ensure that HUD staff with the appropriate level of authority approves extensions to the notices of violation and default cure periods in writing and that documentation is maintained to support such approvals.

  •  
    Status
      Open
      Closed
    2024-CH-0001-003-A
    Closed on July 10, 2025

    Modify the queries used to generate the schedules of properties that accompany the reports to Congress to consider a larger range of dates to ensure that properties that failed consecutive inspections are appropriately identified on all applicable schedules.

  •  
    Status
      Open
      Closed
    2024-CH-0001-003-B
    Closed on August 06, 2025

    Assess and streamline the processes for preparing, reviewing, and approving the reports as appropriate to ensure that the reports are submitted to Congress on or before the required due date.

  •  
    Status
      Open
      Closed
    2024-CH-0001-003-C
    Closed on August 01, 2025

    Implement adequate procedures and controls to ensure that documentation is maintained to support that the reports were submitted to Congress.

Community Planning and Development

  •  
    Status
      Open
      Closed
    2024-FO-0004-001-A

    Develop comprehensive guidance and training for grantees on how to prepare the PR 29 report to ensure that the information collected is reliable, accurate, timely, and in compliance with the Uniform Administrative Guidance for Grants and Cooperative Agreements, specifically 2 CFR 200.302(a)(b) and 2 CFR 200.303

  •  
    Status
      Open
      Closed
    2024-FO-0004-001-B
    Closed on February 09, 2024

    Determine whether the funds that were drawn in error need to be repaid to HUD and whether other remediation actions are appropriate.

  •  
    Status
      Open
      Closed
    2024-FO-0004-001-C

    Follow up with the four grantees without adequate supporting documentation and assess their compliance with the financial management requirements in 2 CFR 200.302(b)(3), which require the financial management system of each non-Federal entity to provide for records that adequately identify the source and application of funds for federally funded activities.

  •  
    Status
      Open
      Closed
    2024-FO-0004-001-D

    Update the CPD Monitoring Handbook to incorporate the review of the PR 29 report when performing financial monitoring reviews.

  •  
    Status
      Open
      Closed
    2024-FO-0004-001-E

    Develop written procedures on how to review PR 29 report submissions and monitor resubmissions, late submissions, and nonsubmissions.

  •  
    Status
      Open
      Closed
    2024-FO-0004-001-F
    Closed on April 20, 2026

    Evaluate and update IDIS to ensure that resubmissions of PR 29 reports are tracked and prior submissions are preserved and correct the system’s misclassification of unsubmitted and uncertified draft PR 29 reports as submitted.